Meeting Notes 1/9/13
Meeting Type: Group Meeting
Attending:
Advisor(s): None
Members: Kyle, Santi, Darryl, Sondra
Excused: None
Action Items
- Finish deliverable
- Schedule advisor times
- Fill Air Tank
- IMU in Mega working together
- Testing actuators
- Lay out the frame and the finished box by next week
- Try processing of some sort on the camera loading program
Meeting Topics
- Deliverable
- Goals for getting back to work
- Meeting Times
Important Notes
Transcript (Notes)
- Most schedules are now finalized
- Group Meeting
- Dr. Clark Meeting TBA
- Dr. Frank Meeting TBA
- Dr. Amin Meeting during senior design periods probably
- Deliverable due Thursday
- Rehash/ update the project plan we already submitted
- Vision team will get together and schedule group work sessions
- Stuart will get air tank filled
- Alex will be in charge of actuator testing
- Darryl will send out sponsors stuff tonight
- To do
- Frame needs finishing touches
- Stuff to do once the machine shop fills
- Vision team
- Meet on Wednesday
- Get computers set up by Friday
- Meeting Friday at 11:35
- Goal is to locate box on a screen as simply as possible using built-in functions